วิธีเล่นบาคาร่า sbobet_นักพนัน ภาษาอังกฤษ_ผลบอล
Site C Construction - July/August 2018
A look at Site C dam construction on the Peace River outside Fort St. John, July and August 2018. BC Hydro Photos
1/16

Powerhouse buttress and main service bay pad, looking upstream, August 2018.
Photo By
BC Hydro

Approach channel excavation on the south bank, August 2018.
Photo By
BC Hydro

Main service bay pad and powerhouse buttress construction on the south bank, August 2018.
Photo By
BC Hydro

The GSS civil works batch plant and crusher, August 2018.
Photo By
BC Hydro

Installation of a tower crane at the powerhouse on the south bank, August 2018.
Photo By
BC Hydro

Installation of the base of a tower crane at the powerhouse, August 2018.
Photo By
BC Hydro

Formwork for the powerhouse draft tubes tailrace on the south bank, August 2018.
Photo By
BC Hydro

Shotcrete application in the south bank drainage tunnel, August 2018.
Photo By
BC Hydro

Powerhouse buttress and GSS civil works laydown area, August 2018.
Photo By
BC Hydro

Transformer assembly at the substation site, August 2018.
Photo By
BC Hydro

Concrete pedestals and concrete being poured in forms for the substation, August 2018.
Photo By
BC Hydro

Substation control building steel structure on the south bank, August 2018.
Photo By
BC Hydro

Excavating the spillway buttress area on the south bank, July 2018.
Photo By
BC Hydro

Testing concrete on the south bank, July 2018.
Photo By
BC Hydro

Trial concrete placement on the south bank, July 2018.
Photo By
BC Hydro

Transformer delivery to the substation, July 2018.
Photo By
BC Hydro
